Evaluation of the PATH-SAFE programme
Evaluation of the PATH-SAFE programme - Timelines and deliverables
This chapter sets out our timelines for the evaluation and the main deliverables and deadlines.
5.1. Evaluation plan
A Gantt chart visualising the planned timeframe for the implementation of evaluation activities is presented in Figure 5. The deliverables along with their deadlines are highlighted in Table 3. The final report will be prepared by June 28, 2024.
Figure 6. PATH-SAFE evaluation Gantt
5.2. Evaluation deliverables and deadlines
Table 3 below shows the main deliverables and their associated deadlines for the project.
Table 3. Main deliverables and deadlines
Deliverable | Phase | Due date |
---|---|---|
Theory of Change for programme | D1 | December 20, 2022 |
Monitoring and Evaluation Plan | D2 | February 24, 2022 |
Evaluation framework report | D3 | March 31, 2022 |
Process and output evaluation – interim report | D4 | September 4, 2023 |
Process and output evaluation – draft final report | D5 | March 25, 2024 |
Outcome evaluation draft final report | D6.1 | March 25, 2024 |
Impact feasibility study | D6.2 | May 3, 2024 |
Final report and dissemination | D7 | June 28, 2024 |
Revision log
Published: 19 July 2023
Last updated: 19 July 2024