West Lothian (Year 3) (Closed)
Wednesday 19 May 2004
18 February 2004
Executive Summary
The Authority's Strengths
Complaints about the Service - An appropriate procedure is in place.
Liaison with Other Organisations - The Authority has in place arrangements for liaison with other appropriate bodies.
Areas for Improvement
Service Plan - A Service Plan has been produced although it does not contain all information required under the Framework Agreement Service Planning Guidance.
Internal Monitoring - A procedure is in place, however it has not been fully implemented.
Documented Procedures - A document control system has been produced however a superseded copy of the supplement to Code of Practice 16 was still in use at the Authority.
Feedingstuffs - A documented procedure for feedingstuffs inspections requires to be produced.